With the roof nearly finished and most windows in place, the construction team are shifting focus to the facility’s interior.
Heating and air ducts rest on ceiling brackets, electrical cables weave through the building, and the walls are taking form with framing for drywall.
Milestones achieved last month include rooftop units, the mechanical penthouse placement, and progress on staff parking.
Looking ahead, drywalling is progressing on all floors, with vital electrical and plumbing components being installed to shape the building’s future.
Written by Joseph Goden